For an expat, retiree or cross-cultural family planning a custom home in Chiang Mai or Lamphun, the drawings and quotation are only part of the project record. A home construction contract in Thailand must also identify the work, price, schedule and responsibilities in terms that both sides can verify.
On 10–11 May 2026, Thailand’s Office of the Consumer Protection Board (OCPB) published information about home-construction disputes and restated key points from the 2016 controlled-contract rules for businesses hired to construct an entirely new residential building. This was a 2026 reminder about existing rules, not a new law introduced in 2026.
OCPB’s explanation says that the agreement for a new residential building should be accompanied by plans and a bill of quantities and prices, commonly called a BOQ. The drawings define the proposed building and technical information. The BOQ records work items, quantities and prices.
Before signing, the parties should be able to match the project name, site, drawing revision, material descriptions, units, quantities and totals across the documents. Where a product is to be selected later, the contract record should identify the allowance or reference price, the approval process and the way any change will be documented. A sales rendering or an informal message is not a substitute for an agreed written scope.
Prospective clients can review Greenery’s house designs and completed-project portfolio when preparing questions for a scope and specification meeting.
OCPB states that payment instalments should correspond to work that has actually been completed. The useful question is therefore not only how many payments appear in the schedule, but what evidence is required before each one becomes due.
Foundation work, structural work, roofing, building services and finishes can each require different inspection records. The contract should state the completion criterion and the person or role authorised to confirm it. Owners should keep the signed contract, quotation, BOQ, receipts, approved change orders, site photographs and milestone records together.
In separate consumer guidance dated 4 July 2025, OCPB advised consumers to examine the work scope and first-payment terms carefully. It also recommended checking the contractor’s history, previous work, reputation and registered capital. These checks provide information; they do not eliminate project risk.
OCPB’s 11 May 2026 explanation states that the contract must address warranty periods and summarises a minimum five-year period for the structure and at least one year for other attached components. A usable contract should also state when the period starts, what work it covers, how a defect is reported and how the contractor will inspect or respond.
OCPB also says that the contract should contain a daily delay-penalty provision. The percentages shown in the agency’s news item are examples, not a universal statutory rate for every agreement. The actual contract should define the rate, the start point, extensions of time and the notice process. Parties should obtain case-specific legal advice where the wording or applicable law is uncertain.
OCPB distinguishes the 2016 controlled-contract framework for constructing a new residential building from the 2023 rules concerning evidence of payment for residential alterations, repairs and improvements. A form designed for one type of work should not be assumed to cover the other without checking the actual scope.
For a Chiang Mai or Lamphun custom-home project, the documents should make clear which work is included in the main contract, which work will be delivered by separate specialists and who coordinates the drawings, approvals, programme and inspections.
Read more about Greenery Design & Construction, then prepare your project questions before you book an initial architect consultation. The initial consultation is free; it does not include free drawings or free house design.
No. Drawings and specifications describe the proposed work, while the BOQ records quantities and prices. They should use consistent references and revisions.
The sources used here do not prescribe one percentage for every project. OCPB advises consumers to examine the first-payment terms carefully and to align payments with work actually completed.
No. A stated warranty period defines contractual responsibility; it does not guarantee that a defect will never occur. The scope, notice method and response procedure still need to be clear.
No. This is an English-language summary of Thai public sources for general preparation. It is not an official translation and does not replace advice on a specific contract.
Note: This article provides general information only. It is not legal advice or an official English translation.